Homes by Hammer Hero: Custom Home Builder in Boulder
Last updated: November 28, 2026
Homes by Hammer Hero is Hammer Hero LLC’s custom home program, and we work as a custom home builder in Boulder on custom homes, ADUs, and high-end remodels. The City of Boulder is its own municipality in Boulder County. Permits, zoning, and Boulder’s energy code are issued and enforced by the City, not by Denver and not automatically by Boulder County. High-end custom homes typically run about $300 to $600 per square foot. Call (720) 327-5898, Monday through Friday, 8:00 AM to 4:00 PM.
Who issues building permits in Boulder?
The City of Boulder’s Planning and Development Services department issues building permits and inspections for lots inside city limits, through the Customer Self-Service Portal.¹ ² Denver’s permit office has no role, and Boulder County does not issue the permit if the lot is inside the city. The city says submitting online reduces processing time by one to two business days, and that it does not offer a pre-review service for building-permit applications.¹ ³
The city’s published processing estimates, which are not guarantees, are:⁴
- An initial completeness check and plan-check fee invoice: 7 business days.
- New-construction permit review, which begins after the completeness check and plan-check fee payment: 7 weeks.
- Other scopes of work: 4 weeks.
- Full review: up to 9 weeks.
- Inspections: 3 business days.
Some projects need another city approval before the building-permit application, including land-use review, technical document review, a Landmark Alteration Certificate, or floodplain review.¹ We confirm those requirements for your lot before design. A soils report is required in areas of potential mass movement, and a grading and drainage plan is required on a slope of 15 percent or greater.¹
Which building and energy codes apply in Boulder?
The City of Boulder builds to the 2024 International Code Council suite, with local amendments in Title 10 of the Boulder Revised Code, effective August 1, 2025.⁵ It also uses the 2024 City of Boulder Energy Conservation Code (CoBECC), effective December 1, 2024, and the 2026 National Electrical Code, as amended, effective August 1, 2026.⁵ ² A design drawn for a Denver lot cannot be submitted unchanged.
The energy code is stricter than a typical International Energy Conservation Code adoption. According to the city:⁶ ⁷
- New construction focuses on electrification. Natural gas equipment and appliances are generally no longer permitted on new construction under the 2024 CoBECC.
- New homes 3,000 square feet and larger must be net-zero energy (an Energy Rating Index of 0). Net-zero, in the city’s definition, means on-site renewable production plus approved community energy purchases equal or exceed the home’s annual energy use.
- New homes under 3,000 square feet must achieve an Energy Rating Index of 30 or less with renewables.
- New homes, ADUs, and additions of 1,000 square feet or less may use the prescriptive residential path instead of an energy model.
We include energy-code compliance in early design and in the written scope, because those measures affect equipment, insulation, and renewable systems.
How does Boulder zoning affect a custom home?
City of Boulder zoning districts regulate use, form (setbacks, height, and coverage), and intensity, including floor area ratio where it applies.⁸ Low-density and estate districts such as RL-1, RL-2, RE, RR-1, and RR-2 are the usual starting point for a detached custom home; we confirm the district on the city zoning map before design.
Floor area ratio caps the size of the house relative to the lot in RR-1, RR-2, RE, and RL-1, and on many RL-2 lots of 8,000 square feet or larger.⁹ For those districts, the city publishes this formula: on a lot of 5,000 to 10,000 square feet, maximum floor area is (lot size × 0.2) + 2,100 square feet.⁹ On a 7,000-square-foot RL-1 lot, that is 3,500 square feet of counted floor area.⁹ Building-coverage limits also apply in those districts.⁸ Some lots sit in a planned unit development, which can change the standards; we confirm any PUD, overlay, floodplain, or historic designation before design.
Can I build an ADU in Boulder?
Often, yes, if the lot is inside the City of Boulder. As of September 1, 2023, ADUs are reviewed and approved through the typical building-permit process.³ They are allowed by right on a lot with a detached dwelling in most zoning districts, including RL-1, RL-2, RE, RR-1, and RR-2. They are not allowed in a short list of districts, including RH-6, MH, BMS, BCS, and IS-1.³ ¹⁰ Owner occupancy is no longer required as of March 8, 2025.³
Standard size limits, from the city’s ADU guide, are:¹⁰
- A detached ADU: 800 square feet maximum (1,000 square feet if it is an affordable ADU or is on a designated historic property).
- An attached ADU: one-half of the principal structure’s floor area or 1,000 square feet, whichever is less (750 square feet if the principal structure is under 1,500 square feet). Affordable and designated-historic attached ADUs can be larger, up to 1,200 square feet or two-thirds of the principal structure, with a 750-square-foot floor when the principal home is under 1,125 square feet.
Detached ADUs require an automatic fire-sprinkler system and an in-property wet-utility permit.³ ¹⁰ Short-term rental of the ADU or the main house is prohibited unless the ADU and rental license were established before February 1, 2019.³ A Hammer Hero ADU typically runs about $150,000 to $300,000. See our ADU cost guide and Denver ADU page.
What if my lot is in unincorporated Boulder County, not the City?
Then this page’s city rules do not apply. Boulder County’s Community Planning and Permitting Department issues building permits for unincorporated county land, and for the Town of Jamestown, not for lots inside the City of Boulder.¹¹ The county currently uses the 2021 International codes, with county amendments that took effect July 1, 2026, and its own BuildSmart residential energy rules, which are different from the City of Boulder’s CoBECC.¹¹ ¹² Accessory-dwelling rules in the unincorporated county have been more limited than the city’s; as of November 2026, the county’s official DC-26-0002 page described a 2026 code update that was still under study after a May 5, 2026 work session.¹³ We confirm whether the lot is inside city limits or in the unincorporated county, and the current county standards, before design.
Do teardown or historic rules apply in Boulder?
They can. Boulder has 10 historic districts. All exterior changes to a designated individual landmark, or to a property in a historic district, need a Landmark Alteration Certificate before the building-permit application.¹⁴ Demolition of a building that is more than 50 years old and is not designated can require Historic Preservation Demolition Review, including when 50 percent or more of the roof or exterior walls is removed, or when a street-facing exterior wall is removed.¹
A replacement home or a substantial addition can also trigger the city’s affordable housing impact fee, which applies to complete building-permit applications submitted on or after January 31, 2026. The city charges $11 per square foot of newly added floor area, with a credit for the existing home’s size. The fee does not apply to homes under 2,000 square feet in total area, and new ADU floor area is exempt. An addition of 500 square feet or less has a one-time exemption.¹⁵ We confirm whether the fee applies and show it in the written scope.
How does Front Range weather affect a Boulder build?
Expansive soils are common along the Front Range (Colorado Geological Survey), and the city requires a soils report in areas of potential mass movement.¹ Hail and snow are documented regional risks (NWS Denver/Boulder). Some city lots also fall in the wildland-urban interface and must meet ignition-resistant construction standards; we confirm that map for your lot.¹
What does a Boulder project cost?
| Project | Hammer Hero range | Notes |
|---|---|---|
| Custom home (Homes by Hammer Hero) | About $300–$600 per sq ft | Includes design coordination, permits, construction, and finishes. Excludes land, utility tap or hookup fees, and landscaping. |
| ADU | About $150,000–$300,000 | Full build including permits and utility hookups; conversions sit at the low end. |
| Pop-top (second-story addition) | About $450–$650+ per sq ft | Structure, roof, and stair work drive the range. |
| Kitchen remodel | About $350–$650 per sq ft | |
| Bathroom remodel | About $450–$750 per sq ft | |
| Basement remodel | About $85–$200 per sq ft |
These are Hammer Hero’s customer ranges, not citywide averages and not bids. We put your scope and price in writing before work starts, including energy-code measures and any applicable city impact fee.
Example (arithmetic, not a bid): a 4,000-sq-ft custom home at $300 to $600 per sq ft is about $1.2 million to $2.4 million for the construction scope. Land, tap fees, and landscaping are separate. Boulder’s floor-area-ratio limits may cap the house below 4,000 square feet on a smaller lot; we confirm the allowed floor area before design.
How long does it take?
| Project | Typical construction time |
|---|---|
| Custom home | About 10–14 months after permits are issued |
| ADU | About 6–9 months after permits are issued |
| Kitchen remodel | About 1–3 months |
| Bathroom remodel | About 3–6 weeks |
| Basement remodel | About 2–4 months |
Design and permitting come first. The city’s published new-construction review estimate is seven weeks after the completeness check and plan-check fee, and a full review can run up to nine weeks; those are city estimates, not guarantees. Landmark review, energy modeling, finish selections, material lead times, and winter weather can add time. You get a written schedule before work starts.
Boulder projects
Project gallery coming. Ask to see completed Hammer Hero work during your consultation.
Who builds custom homes in Boulder?
Hammer Hero LLC builds custom homes in the City of Boulder through Homes by Hammer Hero. We are a licensed general contractor founded in 2015. We confirm the lot is inside city limits, then check zoning, floor-area limits, and energy-code requirements before we design, permit, and build. Custom homes typically run about $300 to $600 per square foot.
Who issues building permits in Boulder?
The City of Boulder’s Planning and Development Services department issues building permits and inspections through its Customer Self-Service Portal. Denver does not, and Boulder County does not if the lot is inside city limits. The city’s published estimate for new-construction permit review is seven weeks after the completeness check and plan-check fee, and is not a guarantee.
How do Boulder’s energy rules affect a new custom home?
New homes must meet the 2024 City of Boulder Energy Conservation Code as well as the 2024 International codes. For new construction, the energy code focuses on electrification and generally does not permit natural gas equipment. Homes 3,000 square feet and larger must be net-zero energy. Smaller homes must meet an Energy Rating Index of 30 or less with renewables.
Can I build an ADU in Boulder?
Often, yes. In the City of Boulder, ADUs are allowed by right in most zoning districts, including the low-density and estate districts, and are reviewed through the regular building-permit process. A standard detached ADU is capped at 800 square feet and needs a fire sprinkler system. A Hammer Hero ADU typically runs about $150,000 to $300,000.
How much does a custom home cost in Boulder?
Hammer Hero’s range for a high-end custom home is about $300 to $600 per square foot, including design coordination, permits, construction, and finishes. Land, utility tap fees, and landscaping are extra. A 4,000-square-foot home works out to about $1.2 million to $2.4 million. That is arithmetic, not a bid.
Is my Boulder-area lot in the City or in unincorporated Boulder County?
That depends on the address. If the lot is inside the City of Boulder, the city issues the permit and applies city zoning and the city energy code. If it is in unincorporated Boulder County, the County issues the permit and applies County zoning, the 2021 International codes, and BuildSmart energy rules. We confirm the jurisdiction before design.
Related pages
- Homes by Hammer Hero: custom home builder in Denver
- ADU builder in Denver
- How much does an ADU cost in Denver?
- How much does it cost to build a custom house?
- Kitchen remodeling · Bathroom renovations · Basement remodeling
- All services
- Contact Hammer Hero
Start a conversation about Boulder
Planning a custom home, ADU, pop-top, or high-end remodel in the City of Boulder? Call Hammer Hero LLC at (720) 327-5898, Monday through Friday, 8:00 AM to 4:00 PM, or use our contact page. Hammer Hero LLC is a licensed general contractor founded in 2015 by Aaron Andricci. Office: 3230 W Mississippi Ave, Denver, CO 80219.
Call (720) 327-5898 Request a consultation
Sources
¹ City of Boulder, Building Permits and Inspections, read November 28, 2026.
² City of Boulder, Planning & Development Services Hub, including the 2026 NEC effective date (August 1, 2026) and the January 31, 2026 impact-fee start date.
³ City of Boulder, Accessory Dwelling Units.
⁴ City of Boulder, P&DS Services (permit processing times), read November 28, 2026.
⁵ City of Boulder, Building Codes and Regulations.
⁶ City of Boulder, Energy Conservation Code.
⁷ City of Boulder, 2024 Energy Code Update Frequently Asked Questions.
⁹ City of Boulder, Floor Area Ratio Guide.
¹⁰ City of Boulder, Accessory Dwelling Unit (ADU) Guide.
¹¹ Boulder County, Building Permits.
¹² Boulder County, BuildSmart.
¹³ Boulder County, DC-26-0002: Accessory Dwelling Units, read November 28, 2026. The page described a May 5, 2026 work session; it did not present an adopted ordinance.
¹⁴ City of Boulder, Historic Districts and Landmark Alteration Certificate Application and Review.
¹⁵ City of Boulder, Affordable Housing Nexus Study / impact fee on replacement homes and substantial additions, Ordinance 8712, fee applies to complete applications on or after January 31, 2026.